Washington State Mechanics Lien: Guide, Process & FAQs
Everything you need to know about the Washington state mechanics’ lien filing process for contractors.
Start Your Washington Lien FilingWhat’s A Washington Mechanics Lien?
A Washington state mechanics lien is a legal claim filed against a property to secure unpaid compensation for labor, materials, or professional services provided during a construction project. Also known as construction liens or materialmans’ liens, these claims are governed by the Washington state mechanics lien statute (RCW 60.04) and are one of the most powerful tools available to contractors, subcontractors, and suppliers for protecting their right to payment.
Washington Lien Deadlines
Missing Washington State mechanics lien deadlines is the most common reason a claim is invalidated. Under state law, contractors must strictly adhere to statutory timelines for preliminary notices and the final claim of lien. Check out the critical dates below.
For Subs/Laborers
Preliminary Notice Deadlines
60 Days
Preliminary notice, a.k.a. Notice of Intent or Notice of Right to Claim Lien, within 60 days from first delivering labor or materials. Who must receive the notice depends on the role of the party that hired the party giving notice.
Send NowMechanics Lien Deadlines
90 Days
Washington mechanics’ liens must be filed within 90 days from last delivering labor or materials.
File NowFor Suppliers/Others
Preliminary Notice Deadlines
60 Days
Notice of Right to Claim Lien within 60 days from first delivering labor or materials. Who must receive the notice depends on the role of the party that hired the party giving notice.
Send NowMechanics Lien Deadlines
90 Days
Washington mechanics’ liens must be filed within 90 days from last delivering labor or materials.
File NowGeneral Contractors
Preliminary Notice Deadlines
60 Days
Under some circumstances, Notice to Owner is required before commencing work. Model Disclosure Statement due before work begins on all residential projects, and commercial projects under $60,000.
Send NowMechanics Lien Deadlines
90 Days
Washington mechanics’ liens must be filed within 90 days from last delivering labor or materials.
File NowHow To File A Mechanics Lien In Washington
Filing a Washington State mechanics lien follows a strict process under state law. Here’s a step-by-step guide.
Confirm Your Eligibility
Under Washington state mechanics lien law, you may file a claim if you furnished labor, professional services, materials, or equipment to improve real property. Suppliers to suppliers are not eligible.
Prepare Your Lien Form
Your Claim of Lien must include the claimant’s name, phone number, and address; the first and last dates labor and/or materials were furnished; the name of the hiring party (person indebted); a property description (legal recommended); the name of the property owner; the lien amount (principal only); and your signature with notarization.
Record The Lien
File your claim at the county auditor’s office where the property is located. If the property spans two counties, record with both. You can file in person, by mail, or electronically. Available methods vary by county.
Send Notice To The Property Owner Within 14 Days
After recording, you must deliver a copy of the lien to the property owner within 14 days in person or by certified/registered mail. Missing this step won’t invalidate your lien, but it disqualifies you from recovering legal fees if you later foreclose.
Enforce Or Release The Lien
A Washington mechanics lien is effective for 8 months from the date of recording. If the owner still hasn’t paid, you can send a notice of intent to lien Washington state (Notice of Intent to Foreclose) to signal you’re ready for court. Once paid, file a release of lien Washington state to clear the property title.
Important
Any incorrect detail can invalidate the entire claim. If you’d like a reliable lien specialist to handle this for you, file a mechanics lien with Northwest Lien.
For a more detailed walkthrough, view our complete step-by-step guide.
Download The FREE Washington Lien Cheat Sheet
"*" indicates required fields
Washington Mechanics Lien Articles
Learn more about how to file a mechanics lien in Washington.
Washington Notice of Intent: How to Send Preliminary Notice in WA
Quick Summary: Washington Notice of Intent to Lien A Washington Notice of Intent to Lien is a formal demand letter…
Read Article
How to Enforce a Mechanic’s Lien in Washington State
More often than not, filing a mechanic’s lien or a construction lien waiver is enough to persuade a property owner to settle their debts. On the…
Read Article
Washington Mechanics Lien Deadlines: When to File?
It’s important to know your lien deadlines! In Washington, you must file a lien within 90 days from last furnishing, though the notice deadlines vary.